Florida construction liens and bond claims follow different deadline sequences, and the triggering event depends on the required notice or filing. The table below summarizes common deadlines for private, bonded-private, and public projects. Preliminary notice rules have exceptions and alternative triggers, so confirm the project’s ownership, bond documents, and your role before relying on a date.
| Action Required | Private Project (Lien) | Bonded Private Project (§ 713.23) | Public Project (§ 255.05) |
|---|---|---|---|
| Notice to Owner / Notice to Contractor | Generally within 45 days of first furnishing for claimants required to serve notice; laborers and parties in direct contract with the owner are generally exempt. | Notice to Contractor generally before or within 45 days after first furnishing, except laborers; an alternative trigger may apply if the bond and Notice of Commencement were not recorded as required. | Notice to Contractor generally before or within 45 days after first furnishing, except laborers; an alternative trigger may apply if the bond was not recorded before work began. |
| Notice of Nonpayment | N/A | No earlier than 45 days after first furnishing; no later than 90 days after final furnishing | Same window as bonded private |
| Record Claim of Lien | Within 90 days of final furnishing | N/A | N/A |
| Serve Claim of Lien on Owner | Before recording or within 15 days after | N/A | N/A |
| File Suit | Within 1 year of recording (or 60 days if owner files Notice of Contest) | Within 1 year after final furnishing | Within 1 year after final furnishing |
| Attorney's Fees Available | Possible | Possible | Prevailing party (§ 255.05) |
One point the table cannot fully capture: punch-list or correction work generally does not count as final furnishing under § 713.01 and does not restart the 90-day clock. Only substantive, contract-required labor, services, or materials count. Returning to fix a defect after your crew has left usually will not extend the deadline to record a Claim of Lien.
The right remedy depends on who owns the property and whether a payment bond was properly furnished and recorded. Private property may support a Chapter 713 lien; a qualifying bond on private work can direct claims to the bond; and public work generally uses a § 255.05 bond claim. Federal projects follow separate law.
On a private construction project where no payment bond has been posted, Florida’s Construction Lien Law (Chapter 713, Florida Statutes) gives contractors, subcontractors, sub-subcontractors, laborers, and material suppliers the right to record a lien against the improved property itself. The lien attaches to the owner’s real estate and can ultimately be enforced through a foreclosure lawsuit, similar in structure to a mortgage foreclosure. Liens are recorded with the Clerk of Court in the county where the property is located. For projects in Tampa and surrounding areas, that means the Hillsborough County Clerk of Courts. Projects in St. Petersburg and Clearwater record with the Pinellas County Clerk, and projects in the Sarasota and Venice area record with the Sarasota County Clerk.
A payment bond that satisfies Florida’s statutory requirements can exempt a private project’s property from lien claims and route eligible claims to the bond. The bond must meet requirements for its amount, timing, and recording with the Notice of Commencement. If those requirements are not met, lien rights may remain. Under Fla. Stat. § 713.23, eligible claimants pursue payment from the contractor and surety rather than the real estate.
Public property, such as a county courthouse, a school, or a municipal road project, cannot be liened. Instead, Florida law requires that a payment bond be posted on public construction contracts above a threshold amount. Fla. Stat. § 255.05 governs these public construction payment bonds, sometimes called Florida’s Little Miller Act. The notice and suit deadlines are strict, and the statute provides for prevailing-party attorney’s fees, which can make litigation more economically viable for claimants with legitimate claims. Federal public projects follow separate federal law (the Miller Act), which carries its own distinct requirements. If your project involves a federal agency, raise that with an attorney immediately, as the federal framework differs meaningfully from state law.
Preserving a construction lien on a Florida private project requires timely notice, accurate recording, and proper service. Each step has its own deadline, and a missed requirement can weaken or defeat an otherwise valid claim. The first question is whether your role requires a Notice to Owner and when that notice period began.
Most lienors other than laborers must serve a Notice to Owner (NTO) before beginning or within 45 days after first furnishing labor, services, or materials. The notice alerts the owner to the claimant’s potential lien rights. A construction lawyer can help determine whether your role requires an NTO and identify the proper recipients. Without a timely notice when one is required, a claimant generally cannot enforce a lien under Fla. Stat. § 713.06(2)(a). A contractor in direct contract with the owner generally does not need to serve an NTO.
A claimant generally must record a Claim of Lien with the Clerk of Court in the county where the property sits within 90 days after final furnishing. Under Fla. Stat. § 713.08(5), the claim must be served on the owner before recording or within 15 days afterward. A late or missed service can make the lien voidable if the delay prejudices someone entitled to rely on service. A construction lien lawyer can review the filing and service steps before the deadline.
If payment is not made, a claimant generally must file a lien foreclosure action within one year after recording the Claim of Lien. An owner or the owner’s attorney can shorten that period by serving a Notice of Contest of Lien under § 713.22, which gives the claimant 60 days to file suit. Missing the shortened deadline extinguishes the lien. A construction lien lawyer can assess the deadline and available enforcement options. Our Florida construction litigation attorneys handle lien foreclosure actions across Hillsborough, Pinellas, Sarasota, and other Florida counties.
Payment bond claims follow a separate process on both bonded private and public projects. Claimants may need to serve a notice to the contractor and a notice of nonpayment before filing suit, with the applicable statute setting the recipient and timing. A construction bond lawyer can identify which statute applies and calculate deadlines from the correct furnishing dates.
On bonded private and public projects, claimants who are not in privity with the contractor generally must serve a written Notice to Contractor before beginning or within 45 days after first furnishing. Laborers are generally excepted. If the required bond was not recorded before work began, an alternative notice period may apply after the claimant receives a copy of the bond. A construction lawyer can check which trigger controls.
When payment has not been received, the claimant must serve a Notice of Nonpayment on the contractor and the surety. This notice may not be served earlier than 45 days after first furnishing and must be served no later than 90 days after the last day of final furnishing. A construction payment lawyer can help confirm the service deadline and recipients. Under § 713.01’s definition of “final furnishing,” punch-list or correction work generally does not restart the 90-day clock. Only substantive, contract-required furnishing counts.
If the Notice of Nonpayment does not produce payment, a claimant may file suit against the contractor and the surety within one year of the last day of furnishing. On public projects under § 255.05, the statute provides for prevailing-party attorney’s fees, which can shift the economic calculus of litigation. Questions about non-payment and business account collections often intersect with bond claims when a contractor has failed to pay multiple parties on the same project.
Owners and general contractors facing a lien or bond claim can review whether the claimant met notice and filing requirements. Florida law also provides procedures to shorten enforcement periods, transfer a lien to security, or challenge a fraudulent lien. The best response depends on project documents, the claim’s history, and the need to clear title or resolve payment exposure.
An owner or the owner’s attorney may serve a Notice of Contest of Lien under § 713.22 to shorten the time for a claimant to enforce a lien. Once served, the claimant generally has 60 days to file suit or the lien is extinguished. Owners should confirm that the notice is properly prepared and served, especially when a pending sale or refinancing makes title timing important.
Under § 713.24, a lien can be transferred from the real property to a cash deposit or a surety bond filed with the Clerk of Court. Once transferred, the lien no longer encumbers the property, allowing a sale or refinancing to proceed while the underlying payment dispute continues. The claimant’s rights are preserved against the bond or deposit rather than the real estate. This mechanism is particularly useful for developers and owners in the Tampa Bay area who cannot afford a title cloud during a refinancing or sale.
Florida law treats a lien as fraudulent if the lienor willfully exaggerates the amount claimed, includes a claim for work not performed or materials not furnished, or prepares the claim with willful and gross negligence amounting to a willful exaggeration. A court may declare a fraudulent lien unenforceable, and the statute provides remedies that can include damages, costs, and attorney’s fees. A construction law firm can review a disputed claim before either side escalates the dispute.
A frequent and costly mistake is measuring a deadline from overall project completion rather than from the claimant’s own final furnishing. A subcontractor who finishes a scope in March may have a lien-recording deadline before the general contractor completes the project in June. That distinction matters because each claimant’s furnishing dates can control their own notice and filing periods.
Other patterns that frequently cause problems:
For a broader look at how to protect your business from these and other legal pitfalls, our blog covers avoiding legal pitfalls as a Florida construction company in more detail.
Brick Business Law, P.A. is a Florida business law firm that helps contractors, subcontractors, suppliers, owners, and general contractors manage payment disputes. Our attorneys work with clients to preserve lien and bond claims, contest disputed claims, and weigh resolution options. The goal is to protect payment rights and business operations while helping clients choose their next step.
Our law firm serves clients across Hillsborough, Pinellas, and Sarasota counties, with offices in Tampa, St. Petersburg, and Sarasota. We also serve clients in Venice, Orlando, and throughout Central Florida. Liens are recorded with the Clerk of Court where the property sits, so local filing procedures matter. A law office familiar with those county processes can help leadership track the right deadlines and keep a payment dispute from disrupting a project.
As a construction law firm, Brick Business Law connects legal strategy to cash flow, contract relationships, and business continuity. Our construction lawyers and business attorneys can help evaluate claim options before, during, and after a dispute develops. For businesses looking for an ongoing legal partner, our law firm also provides business-focused counsel beyond a single claim.
Generally, no. Under Florida’s statutory definition of “final furnishing,” only substantive, contract-required labor and materials count toward the deadline. Punch-list work or correction of defective work typically does not restart the 90-day window to record a Claim of Lien.
Missing the 45-day NTO deadline generally means you cannot record an enforceable lien against the property. In some cases, alternative remedies may still be available, but the lien right itself is typically lost. Consulting with a construction attorney as soon as possible after first furnishing is the safest approach.
Yes. Under § 713.24, a lien can be transferred from the property to a cash deposit or surety bond filed with the Clerk of Court. This clears the property’s title while the dispute over payment continues against the substitute security.
Section 713.23 governs payment bonds on bonded private projects, while § 255.05 governs payment bonds on public construction projects. Both require strict notice and filing deadlines, but § 255.05 also provides for prevailing-party attorney’s fees, which § 713.23 does not guarantee in the same way.
No. Federal public projects are governed by the federal Miller Act, which is a separate statute with its own notice and suit requirements. If your project involves a federal agency or federal property, you should speak with an attorney promptly, as the federal framework differs from Florida’s Little Miller Act.
A recorded Claim of Lien is effective for one year from the date of recording unless a lien foreclosure lawsuit is filed or the lien is otherwise discharged. If the owner files a Notice of Contest of Lien under § 713.22, that window shortens to 60 days from service of the notice.
Attorney’s fees may be available in lien foreclosure actions depending on the contract and the outcome. On public bond claims under § 255.05, the statute expressly provides for prevailing-party attorney’s fees. Whether fees are recoverable in any specific case depends on the facts, the contract language, and the applicable statute.
Payment deadlines in Florida construction do not wait for negotiations to conclude or disputes to cool down. If a deadline is approaching, or if you are not sure when your clock started running, the time to act is now. Schedule your free consultation with Brick Business Law, P.A. and get clarity on where your rights stand before a statutory deadline runs.