Lumber, steel, concrete, or copper jumps in price after you’ve signed. Suddenly a profitable job is eating your margin. The first question most contractors ask is whether the customer has to cover the difference. The answer starts with your contract, and what you do in the next few days can matter as much as what it says.
Raising the price, slowing down, or walking off the job without a clear contractual basis can turn a cost problem into a breach of contract claim against you. At Brick Business Law, P.A., we help Florida contractors work through these decisions with the numbers in view: margins, schedule, the customer relationship, and the risk of a dispute.
Can You Pass a Material Price Increase On to the Customer?
Usually not, unless the contract gives you a way to do it. A fixed-price contract generally requires you to complete the agreed scope of work for the agreed price. A spike in material costs, on its own, does not change that.
Estimates and proposals can be different. Whether an estimate is binding depends on whether it became part of the agreement and what the customer accepted. Before you send a revised price, pull together the estimate, proposal, purchase order, contract, and any emails that changed the terms. Those documents decide your options.
Does Your Contract Have a Price Escalation Clause?
A price escalation clause lets the contract price change when specified costs rise after signing. Most spell out:
-
Which materials are covered
-
A threshold, such as a percentage increase, before an adjustment applies
-
How the adjustment is calculated
-
What documentation you must provide
-
Notice deadlines
Miss a notice deadline or skip the required documentation, and you may lose an adjustment you were entitled to. Read the whole clause before you send a revised invoice.
Is the Higher Cost Actually a Change in Scope?
A change in scope is different from a higher cost to do the same work. If the customer adds work or changes material specifications, your change order process may let you adjust the price. A supplier charging more for the same materials is not a scope change, and labeling it one tends to damage trust quickly.
Can a Florida Customer Refuse a Contractor’s Price Increase?
Yes, if the contract does not allow the increase. The customer can generally hold you to the agreed price. Whether you have another way to recover the extra cost depends on the agreement and the facts, which is why your next step matters.
Can You Stop Work if the Customer Says No?
Stopping work is the move that most often turns a pricing problem into a lawsuit. Without a contractual or legal right to suspend performance, the customer may claim breach of contract and seek damages for delays, the cost of a replacement contractor, and other losses.
Before you suspend work, compare two numbers: what it will cost to finish the job at a reduced margin, and what you could owe if you stop. In many cases, finishing and negotiating is cheaper than defending a breach claim.
“The contractors who come out of a price spike in the best shape usually document the increase early, raise it in writing, and give the customer a reasonable proposal before anyone talks about walking off the job.”
— Kevin Brick, Brick Business Law, P.A.
What Can You Do if the Contract Has No Escalation Clause?
Negotiate, and do it with evidence. Customers respond better to documented numbers than to a request for more money. Gather:
-
Original and revised supplier quotes
-
Supplier invoices showing the new prices
-
Written price-increase notices from suppliers
-
Correspondence with suppliers or subcontractors about the change
A reasonable proposal might split the increase or adjust only the materials affected. Many owners would rather share a documented cost than restart a project with a new contractor.
Put Any Agreed Price Change in Writing
If you reach a deal, document it in a written contract amendment signed by both parties. Florida law may recognize oral changes to a contract in some situations, but enforceability depends on the contract and the facts. A phone call or handshake is a weak record for a significant price change.
Will a Force Majeure Clause Help?
Maybe, but don’t count on it. A force majeure clause covers specified events outside the parties’ control that interfere with performance. Higher prices alone usually don’t qualify. Whether yours applies depends on its exact wording and what caused the increase.
How Can Florida Contractors Protect Future Jobs From Price Swings?
Once the current job is handled, fix the contract you’ll use on the next one. A few terms can shift a lot of risk:
-
Limit how long your quote is valid. A short pricing window, such as 30 days, keeps an old number from binding you months later.
-
Tie adjustments to a published index. Linking escalation to a recognized price index for the material gives both sides an objective number.
-
Set a cost-sharing formula. For example, you absorb increases up to a set threshold, and costs above it are split or passed through.
-
Use allowances for volatile materials. Pricing those items separately keeps one spike from wrecking the whole bid.
-
Write notice and proof requirements you can actually meet in the field.
The goal isn’t to win every pricing argument. It’s to make sure both sides know how a cost spike will be handled before it happens, so a supplier increase doesn’t become a customer dispute.
When Should a Contractor Call a Business Lawyer?
Before you raise a price, stop work, or send a demand letter. Those steps can change your legal position, and they are hard to undo. A business lawyer can review the agreement, tell you where you stand, and help you choose the option that protects both the job and the relationship.
Brick Business Law, P.A. helps contractors and other Florida businesses with contract drafting and review, negotiations, and breach of contract disputes. From our offices in Tampa, St. Petersburg, and Sarasota, our attorneys focus on the business result, whether that means protecting your margin, keeping an important customer, or responding to a dispute that has already started.
Related: If a customer is holding back payment while you sort out pricing, read Before You Sign: Contract Provisions That Can Affect Construction Payments.
|
If rising material costs are squeezing a current project, or you want stronger contracts for the next one, schedule a free consultation with Brick Business Law or call 813-669-0122. |
This article provides general information, not legal advice. Reading it does not create an attorney-client relationship. For advice about your situation, contact a lawyer.